Newsflash
Home
Mt. Blue Regional School District
MBHS April Update PDF Print E-mail
Written by Administrator   
Tuesday, 07 May 2013 08:57

May 3, 2013



Michael R. Cormier, D. Ed.   

Superintendent of Schools

Mt. Blue Regional School District

115 Learning Lane

Farmington, ME  04938-7039


Re:      MOUNT BLUE HIGH SCHOOL LEARNING CAMPUS

Subj:    Monthly Update on Schedule and Safety


Dear Dr. Cormier:


What follows is a brief description of the work accomplished during the month of April at the Mount Blue High School Campus.  The contractors continue to have good weather with temperatures slightly above normal and with snow and rainfall slightly below average.


Work accomplished during April included the following:


  • Exterior sitework was restarted during April.  Foul line fences were installed along the softball and baseball fields.  Work continued on the irrigation system for the fields.  Final roof drain connections were made to various catch basins at the front of the “B” and “A” wings.


  • Vapor barrier, rebar and 115 cubic yards of concrete were poured on the first floor of the “A” wing in the area of Main Street and the administrative area.


  • Formwork was continued for the concrete steps on the lower half of the auditorium.


  • The masons are nearing completion of the interior concrete block with work done in the area of the student and public toilets, the school store, the health office, and the branch bank.


  • The construction crane which had installed steel and wood glue lam beams was pulled off site during the third week of April.


  • The temporary scaffolding which was built in the auditorium was taken down upon completion of the drywall ceiling with its associated lights and HVAC ductwork.


  • Stair railings were installed at Stair #S2 and the second floor of the “A” wing along Main Street.


  • Carpenters continue to install wood blocking for interior partitions in the “A” wing at the entrance canopy and at the vestibule roof.


  • Waterproofing continued with caulking and exterior sealant, as well as air barrier membrane and self-adhered flashing at the curtain wall frames and the northeast corner of the three-story classroom “B” wing.


  • The roofing subcontractor completed the metal siding on the east, west and north sides of the auditorium and south side of the music room.


  • The window subcontractor continued installing the curtain wall windows at the “B” and “A” wings and has begun installing waterproof mullions between the windows.


  • Gypsum wallboard installation continued on the first and second floor of the administrative “A” wing, the acoustical clouds in the auditorium, the mechanical mezzanine and the digital media, TV studio and TV control rooms.


  • Painting continued with block filler in the wrestling, music room, practice rooms, health areas, as well as painting of interior walls and partitions on the first floor of the “B” wing and the acoustical clouds in the auditorium.


  • The porcelain wall tile was completed at the corridor entrances to the student toilets on the first, second and third floors of the “B” wing, as well as the floor and wall tile for the special education and early childhood toilets.


  • Carpeting was installed on the second and third floors of the “B” wings.  The linoleum continued to be installed on the second and third floors of the “B” wing.


  • Toilet partitions and toilet accessories were installed on the first, second and third floors of the “B” wing.  Wood doors and hardware at the classroom and heat pump closets continued throughout the three-story wing.


  • Lockers arrived for the second and third floors of the “B” wing.


  • Ceiling grid hangers and perimeter angles were hung on the first and second floors.  


  • Science casework and classroom casework with countertops and windowsills were installed throughout the three-story classroom wing.


  • Sprinkler system runouts were continued to sprinkler head locations and sprinkler head drops were made in the classrooms throughout the “B” wing.


  • The plumbing subcontractor worked on bathrooms throughout the “A” and “B” wing installing waste, vent, and domestic water to all toilet rooms and classroom sinks.


  • Geothermal heat pumps continued to be installed with factory start up at the “A” wing.


  • Ductwork was insulated and sealed.  Conduits and device boxes were set for controls for the “A” wing HVAC equipment and CO2 sensors.


  • Electrical system installation continued in the “A” wing, as well as installation of light fixtures in both the “A” and “B” wing.


  • Sky Stream and Wind Spire windmills were both made operational after having had internal power controls replaced.


  • The construction testing laboratory continued to perform concrete testing, compaction testing and rebar observations, as well as inspections on structural steel, joists and steel deck at the “A” and “C” wings.


  • One third-party inspection of the site was made for DEP during the month of April.


  • Wright-Ryan Construction continues to have two full time construction superintendents on site.  The general contractor meets daily and weekly with the subcontractors to review scheduling and coordination.  All contractors meet weekly to discuss job site safety and emergency response protocol.


  • Mt. Blue School District personnel continue to meet every two weeks with representatives from the State of Maine and the architect’s office to review the progress of the work, the construction quality and job site safety.


Please feel free to call should you have any.


Very truly yours,

PDT ARCHITECTS





Lyndon D. Keck, AIA, LEED AP

Maine Licensed Architect

Principal


MBHS-SafetyLetter-03MAY13-Cormier-ldk

 
Press Release PDF Print E-mail
Written by Administrator   
Wednesday, 24 April 2013 19:07

Mallett School

Kindergarten, Thursday, May 30, 8:00 to 4:30, please call the 778-3529 for an appointment.


Pre-K, Thursday, May 16, 8:00 to 4:30 or Friday, May 17, 8:00 to 3:00, please call 778-3529 for an appointment.


Your child must be five years old on or before October 15, 2013 in order to register for kindergarten. For Pre-K, your child must be four years old, on or before October 15, 2013.


At registration, you will need your child’s original birth certificate, up to date immunization records, a recent photo of your child, and filled out parental questionnaire and medical history forms. New this year -registration packets should be picked up at Mallett School prior to registration.


Students who are currently enrolled in Mallett, Cushing or Cape Cod Hill School’s Pre K program, do not need to re-register for kindergarten.

 
MBHS March Update PDF Print E-mail
Written by Administrator   
Monday, 08 April 2013 11:08

March 29, 2013



Michael R. Cormier, D. Ed.   

Superintendent of Schools

Mt. Blue Regional School District

115 Learning Lane

Farmington, ME  04938-7039


Re:      MOUNT BLUE HIGH SCHOOL LEARNING CAMPUS

Subj:    Monthly Update on Schedule and Safety


Dear Dr. Cormier:


This letter provides a brief description and overview of the work accomplished during the month of March on the Mt. Blue High School campus.  March was a drier month than normal with slightly above average temperatures.


Work accomplished during March included the following:



  • Gravel and structural fill were placed in the auditorium and entry administration area in preparation for compaction and future concrete floor slab.



  • Concrete was placed on the new second floor of the auditorium wing and on the first floor of the administrative “A” wing.



  • The mason laid out masonry for toilet rooms and offices on the second floor adjacent to the auditorium.



  • The contractor filled the auditorium space with temporary scaffolding and built a temporary platform floor 4’ below the auditorium steel trusses to enable all trades to work on the ceiling components of the auditorium.  This work included installing the tubular steel catwalk, hanging acoustical drywall baffles, installing auditorium lights, auditorium ductwork and sprinkler systems.





  • Carpenters continued to install plywood sheathing on the curved administrative roof, as well as roof insulation and framing for clerestory windows at the curved roof line.



  • Contractor is installed thermal and moisture protection and metal siding on the south side of the three-story “B” wing, and installed air barrier and exterior caulking systems on south side of “B” wing.



  • The window subcontractor continues installation of the curtain wall windows at the “B” wing and began fabrication and installation of the clerestory windows over the “A” wing adjacent to the auditorium.



  • Painting continued in the three-story academic block with primer and second coat painting on classroom walls, as well as painting of the installed acoustical clouds in the auditorium.



  • Floor installation began in the three-story academic building with the installation of carpet and linoleum flooring in classrooms.



  • The elevator in the three-story building was installed with work continuing on electrical controls and elevator lighting.



  • The sprinkler subcontractor continued to install sprinkler mains in the administrative wing and sprinkler heads throughout the three-story “B” wing.



  • The plumbing subcontractor continued making connections for permanent roof drains and plumbing fixtures in bathrooms in the “B” wing.



  • Installation of the heat pump water piping continued through March, as well as duct work for the west side of the administrative wing.



  • Electrical systems installations continued with the installation of panels and steel conduits in the auditorium and the installation of light fixtures on the first and second floor of the three-story academic wing.



  • Wiring for the clocks, speakers and security system continued in the three-story academic building.  



  • Cabinetry was delivered and installed for the first floor science rooms and art rooms in the “B” wing.



  • The testing laboratory continued with compaction testing and concrete testing.



  • Wright-Ryan Construction continues to have two full time construction superintendents on site.  The general contractor meets daily and weekly with the subcontractors to review scheduling and coordination.  All contractors meet weekly to discuss job site safety and emergency response protocol.



  • Mt. Blue School District personnel continue to meet every two weeks with representatives from the State of Maine and the architect’s office to review the progress of the work, the construction quality and job site safety.


Please feel free to call should you have any questions concerning the progress schedule or safety on the job site.


Very truly yours,

PDT ARCHITECTS





Lyndon D. Keck, AIA, LEED AP

Maine Licensed Architect

Principal


MBHS-SafetyLetter-29MAR13-Cormier-ldk

 
Budget 2013-2014 PDF Print E-mail
Written by Administrator   
Friday, 12 April 2013 08:59

To:  Members of the Board of Directors

From Michael Cormier, Leanne Condon, and the Budget Sub-Committee of the Board

Re:  Proposed Budget for 2013-2014

Date:  April 2, 2013


It is time, once again, to write an explanation and rationale for the proposed budget.  Please note that this is Mike’s last cover letter for a budget book and Leanne’s first attempt -- as part of the superintendent internship.


For another year we find ourselves in trying times.   To borrow from another ~ “During these continued tough economic times, writing a sensible, fair budget, that provides real opportunities . . . is always tough” (Senator Jeanne Kohl-Welles).


The Budget Sub-Committee established goals and priorities for this budget process to include:

1.  Maintain teacher-pupil ratios within our schools.

2.  Retain current programming.

3.  Address needs in the area of special education.

4.  Address increase in fixed cost charges.


In keeping with our goals and priorities, we built a budget that has an increase of $479,753, or 1.7%.  You may be aware that there have been some changes in state funding of education, and there has been discussion by the state whether or not to ask local districts to cover teacher retirement; should retirement get shifted to the local school district, the budget increase is $793,801, or 2.7%.


Although we do not have the official figures from the state as we go to “press,” we have a preliminary calculation of the adjusted state share to RSU #9 of $18,129,866.  This is up $47,955 from 2012-13.  These figures do not take teacher retirement cost sharing into consideration.


Other issues to be aware of include the state enacting a curtailment that will withhold $135,250 from our 2013-14 and 2014-15 budgets.   Our balance forward is decreased by $240,000 for this year’s budget proposal;  budgets are so tight that there is very little left at the end of the year.   


Our fixed cost increases for health, building and fleet insurances, student tuition, negotiated salaries and related taxes, facility and grounds repairs account for an increase of about $617,000 and is offset by a decrease of $358,860 in bonded debt payments.


As an administrative team, we acknowledge the need for a day-treatment program for special education.   There is also a demand for Foster Career and Technical Center programming to include a half-time pre-engineering course, increase the existing composites class to full time, and bring in a full-time CADD program.  All of these program changes bring additional revenue over time, but the members of the budget sub-committee agreed it was not prudent at this juncture to increase the burden to our local taxpayers.


Reductions in school supplies, textbook accounts, and materials are now in the fourth year.  Money to repair facilities was kept to a minimum with focus on the areas needing critical updating to maintain a safe environment for students and staff.


Extended-day and -year programming, for general and special education are again funded in part by federal grant money and also by the local school budget.


Mt. Blue Regional School District continues to be a highly effective and efficient school system.  We rank eighty-nine out of one-hundred-and-three K-12 public school systems in the State.  Eighty-seven percent of school systems in the State spend more per student than Mt. Blue RSD based upon 2011-12 figures.  The average cost for K-12 education in the State is $9,727 per pupil; the average cost in RSU No 9 is $8,446 per pupil or $1,281 below State average.


We urge you to be aware of the continued changes in state funding of education as we move through this budget process.  We submit a budget to you that supports our goals and priorities, maintains current programming, and is fiscally responsible.  We appreciate your support as we work together to present a budget to our local towns.

 

The  attachments are breakdowns for each scenario.

Last Updated on Friday, 12 April 2013 09:03
 
MBHS February Update PDF Print E-mail
Written by Administrator   
Tuesday, 05 March 2013 15:01
March 1, 2013


Michael R. Cormier, D. Ed.   
Superintendent of Schools
Mt. Blue Regional School District
115 Learning Lane
Farmington, ME  04938

Re:      MOUNT BLUE HIGH SCHOOL LEARNING CAMPUS
Subj:    Monthly Update on Schedule and Safety

Dear Dr. Cormier:

Work has continued at a rapid pace through January and February, with the contractor having large crews throughout the work weeks.  The contractor had estimated they had spent over 12,000 man hours of time during the month of February with an average work crew size of 75-80 men each day.  Weather conditions have been average with slightly more precipitation than normal in February and temperatures above average for the month.

Work accomplished in February included the following:

  • The contractor has been thawing the ground inside the building with ground heaters, heating tubes and blankets.  Concrete floor slabs have been placed in the auditorium with cross aisles and auditorium risers for the upper seating.  Concrete slabs were also placed along the auditorium corridor serving digital media, the TV. studio and sound studio.  Concrete floor slab was also placed on the mechanical mezzanine, as well as thickened equipment pads for ventilation and heat recovery equipment.

  • The masonry subcontractor worked on interior concrete block walls in the music wing, the athletic support rooms, toilets, and hallways.  Masonry also continued on walls in the three-story “B” wing.  Exterior brickwork on the south side of the three-story “B” wing was also installed.




  • Structural steel columns, beams, joists and decking were installed for the sloping roof of the “A” wing and new administrative offices.  Bridging and decking were welded and installed at the new “B” wing stairwell and second floor outside the auditorium.

  • A testing laboratory has been on site inspecting bolted and welded connections for structural steel joists and deck at the “A” and “C” wing.

  • Carpentry crews continue to install wood blocking for interior partitions in the three-story “B” wing.  Installation of the wood glue lam columns, beams and decking for the Main Street hallway was completed.  Carpentry crews also installed roof overhang outriggers and completed wood blocking for the parapets at the mechanical room and auditorium.

  • The roofing contractor completed the roof installation at the auditorium and second story mechanical mezzanine.  Windows and curtain wall systems continue to be installed at the three-story “B” wing with exterior and interior caulking and gasketing being installed on both sides of the glass windows.

  • The drywall contractor has continued to install steel stud framing, insulation, and fire code gypsum wallboard throughout the three-story “B” wing.

  • Painting began on the interior walls of the second and third floor of the “B” wing.

  • The flooring contractor installed and grouted floor and wall tile for the toilets and staff toilets on the second and third floors.  Installation of the porcelain tile began at corridor walls and toilet rooms.  Ceiling tile hangers, grids and angles were installed on the second and third floors.

  • Science room laboratory cabinets and casework was installed on the second and third floors.  Countertops and sills were begun at windows and curtain walls.  Classroom cabinets were also installed on the second and third floor classrooms.

  • Sprinkler main pipes have been run down the corridors of the three-story building.  Sprinkler head locations have been started in the “A” wing.

  • Sanitary and vent piping, as well as domestic cold and hot water pipes were set in the bathrooms and science rooms, as well as piping for the geothermal heat pumps installed in the three-story classrooms.

  • Electronic controls were installed for heat pump units, fans and energy recovery units at the three-story building.  Mechanical installation continued on cold and hot water pipes throughout the building.

  • Power wiring and electrical devices were installed in the three-story building, as well as fire/audio/and visual alarms as part of the life safety systems.

  • The earthwork contractor continued to work inside of the “A” wing backfilled trenches and compacted sub-grade soils in preparation for concrete slab pours in the “A” wing.

  • The construction testing laboratory was observed reinforcing bar placements, concrete placements and concrete testing.

  • One third party engineering inspection of erosion control measures was done on behalf of DEP during the month of February.

  • Wright-Ryan Construction continues to have two full time construction superintendents on site.  Weekly subcontractor meetings are held to review scheduling and general site safety.  The contractor’s construction superintendents meet weekly with Mt. Blue School District personnel to discuss safety and emergency response protocol.

  • Mt. Blue School District personnel continue to meet every two weeks with representatives from the State of Maine and the architect’s office to review the progress of the work, the construction quality and job site safety.

Please feel free to call should you have any questions concerning the progress schedule or job site safety.

Very truly yours,
PDT ARCHITECTS




Lyndon D. Keck, AIA, LEED AP
Maine Licensed Architect
Principal

MBHS-SafetyLetter-01MAR13-Cormier-ldk
 
« StartPrev12345678NextEnd »

Page 1 of 8

District Calendar

No events
May 2013
M T W T F S S
29 30 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31 1 2
June 2013
M T W T F S S
27 28 29 30 31 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30